Toilet to be constructed on top of a slab with dimension 4 feet x 5 feet, so for this job, there is a 4inch dia UPVC Pipe drilled in to the slab, make sure you have the correct gap between the wall the pipe.
|
Bench marked for floor screeding
Courtesy of YD Works |
Point "A" is the floor drain after drilling hole of 2inch with a pipe fitted, than find the top level of drain and find the top level of "B", make sure the levels differs by 12mm, so that it creates a slop. "C" is where WC is to be fitted.
|
Floor screeding completed
courtesy of YD Works |
ones the floor screeding is completed, now that there is a slop of 12mm from one end to the drain, now that its ready for tiles work
|
floor tiles completed |
|
Wall Tiles completed |
after the tiles is completed, fill the gaps with white water resisting cement. after all the caps been filled, fit the WC on top of the pipe and secure the WC with sealant.
No comments: